These rail transit stations to open this year or the next

2020-01-15 14:32:37

Train of the Loop Line (Picture provided by Chongqing Rail Transit Group)

CHONGQING (CQNEWS) -- This year, Chongqing will continue focusing on the construction of urban rail transit network. What is the current situation of Chongqing rail transit lines under construction? Recently, Chongqing Rail Transit Group released the status of lines under construction and the progress of various projects.

Hualong – Fengmingshan section of Loop Line to open before the Spring Festival next year

The Loop Line starts from Chongqingxi Railway Station, Shapingba District, passes Shapingba, Chongqingbei Railway Station South Square, Shangxinjie and Olympic Sports Center, and returns to Chongqingxi Railway Station.

The total length of the line is about 51 km, with 33 stations. The line is of metro system and As-typed train is adopted.

By the end of December 2019, the section from Chongqing Library to Chonqingbei Railway Station South Square to Erlang has been opened to traffic.

The civil engineering of Hualong — Chongqingxi Railway Station — Fengmingshan Section has been basically completed, and the Rail Transit Group will carry out subsequent installation and decoration and system equipment installation works, striving to open the line to traffic before the Spring Festival next year.

Chaotianmen — Xiaoshizi section of Line 1 is expected to be opened by the end of this year

Chaotianmen — Xiaoshizi section of Line 1 starts from Chaotianmen Station, Yuzhong District and ends at Xiaoshi Station. After completion, it will be connected with Line 1 for operation. The total length of the line is about 1km, with Chaotianmen Station. The line is of metro system. The line is expected to be completed and open to traffic by the end of this year.

Dashiba — Tiaodeng of Line 5 is about to be opened before the Spring Festival of next year

The Phase I of Line 5 starts from Garden Expo Center Station, Yubei District, with the general trend from north to south and ends at Tiaodeng Station, Dadukou District. The total length of the line is about 40 km, with 25 stations. The line is of metro system and As-typed train is adopted.

By the end of December 2019, Phase I of Line 5 Garden Expo Center Station — Dashiba section has been opened to traffic. The Dashiba — Tiaodeng section and Zhongshutuo Station of Phase I of Line 5 have not yet entered the site for construction. Hongyancun Station, Xietaizi Station and Chongqing West Station are in the process of main structure construction. The main structures of the remaining 11 stations have been completed, and the equipment installation and decoration works have been completed by more than half.

The Rail Transit Group is speeding up the construction of Dashiba — Tiaodeng section of Phase I, Line 5, and key node projects are also being implemented in an orderly manner, striving to complete and open to traffic before the Spring Festival next year. In addition, Dashiba — Shiqiaopu section is expected to be completed and open to traffic by the end of next year.

The post-station project of Phase II of Branch Line, Line 6 has been implemented

Phase II of Branch Line, Line 6 starts from Yuelai Station of Phase I, Branch Line of Line 6 and ends at Shaheba Station. The length of the line is about 14 km, with 7 stations. The line is of metro system and B-typed train is adopted.

By the end of December 2019, the civil engineering project for Phase II, Branch Line, Line 6 had been basically completed, and the post-construction project has been put into operation in the near future.

Phase II of Line 9 to carry out civil construction

Phase II of Line 9 project starts from Xingke Avenue Station Phase I of Line 9, passes Chunhua Avenue, Langui Avenue, East Third Road of Central Park and Zongyi Road, and ends at Huashigou Station. The total length of the line is about 8km, with 5 stations. The line is of metro system and As-typed train is adopted.

Post-station general contracting bidding for Phase II of Line 10

Phase II of Line 10 starts from Liyuchi Station of Phase I of Line 10, passes through Zengjiayan, Auditorium, Qixinggang, Nanbin Road, Nanping, Wanshou Road and Nanhu, and ends at Lanhua Road Station. The total length of the line is about 10km, with 8 stations. The line is of metro system and As-typed train is adopted. 

By the end of December 2019, civil engineering construction is being carried out in all sections of Phase II, Line 10. (Translated by Luo Juan, Fathom Language Limited)

Editor:Jiang Yiwei