Chongqing to open three more rail transit lines within the year

2022-10-18 14:20:00

CHONGQING (CQNEWS) -- The reporter recently learned from Chongqing City Transportation Development & Investment Group that the previous three quarters have seen the completion of urban transportation infrastructure construction, in which 33.39 billion yuan were invested. The investment includes 28.44 billion yuan invested in rail transit projects, which hit a record high for the same period.

The rail transit construction over the previous three quarters has progress at a high speed

It is learned that Chongqing City Transportation Development & Investment Group now has 12 rail transit projects under construction, which cover 254km. The four phases of the rail transit project have been in full swing, with 46 stations and 28 intervals entering the main construction stage.

The second phase of Line 9, the northern extension of Line 5, and the second phase of Line 10 from Nanbin Road to Liyuchi, which will be opened at the end of this year, have been in a test run (without passengers). On their completion, the mileage of Chongqing rail transit will top 500km. The second phase of Line 10, in particular, will greatly ease the traffic pressure from river-crossing transport and the passenger flow of Lianglukou Station.

Line 15, the express line of urban rail transit from Liangjiang International Movie City to Zengjia, is the east-west backbone of urban planning and construction in Chongqing. At present, the first phase of the project has started the construction of stations and intervals, and finished the roofing of Liangjiang Avenue Station and Xiuhu Road Station. Liangshan Tunnel, the key node of the phase II project, has started the construction of the main line, and the construction of Liaojia River Bridge is also progressing successfully.

Jinyun Mountain Tunnel, Zhongliang Mountain Tunnel, Tongluo Mountain Tunnel of the express line of Line 27, have all started the construction of their main lines. Lugiao North Station, Chafu Road Station, and Guangyang Bay Station of the first phase of Line 24 have also started the construction of the main structure. Line 18 has completely entered the later construction phase. Half of the excavation work of Yunwu Mountain Tunnel, the control project of suburban (regional) railroad Bitong Line, has been finished. The special line of Guanba Railway has been opened to traffic. 77% of Qiaopingshan Tunnel, the control project of Chongqingdong Station Backbone Road (Phase I), has been completed.

In addition, the group will start the construction of phase I of Line 7 and phase I of Line 17, and speed up the preliminary construction of suburban (regional) railroads, Yongchuan Line and Nanchuan Line this year, so as to facilitate the travel for the public. (Translated by Cai Xinyu, Fathom Language Limited)